Direct Labor Standard Cost and Variances

labor rate variance

If there is no difference between the standard rate and the actual rate, the outcome will be zero, and no variance exists. When a company makes a product and compares the actual labor cost to the standard labor cost, the result is the total direct labor variance. In this case, the actual hours worked are 0.05 per box, the standard hours are 0.10 per box, and the standard rate per hour is $8.00.

An adverse labor rate variance indicates higher labor costs incurred during a period compared with the standard. In this question, the Bright Company has experienced a favorable labor rate variance of $45 because it has paid a lower hourly rate ($5.40) than the standard hourly rate ($5.50). The combination of the two variances can produce one overall total direct labor cost variance. An unfavorable materials price variance occurred because the actual cost of materials was greater than the expected or standard cost.

  1. For example, a rush order may require the payment of overtime in order to meet an aggressive delivery date.
  2. In this case, the actual hours worked are 0.05 per box, the standard hours are 0.10 per box, and the standard rate per hour is $8.00.
  3. Later in Part 6 we will discuss what to do with the balances in the direct labor variance accounts under the heading What To Do With Variance Amounts.
  4. We assume that the actual hour per unit equal to the standard hour but we need to pay higher or lower due to various reasons.

The actual amounts paid may include extra payments for shift differentials or overtime. For example, a rush order may require the payment of overtime in order to meet an aggressive delivery date. Finance Strategists has an advertising relationship with some of the companies included on this website. We may earn a commission when you click on a link or make a purchase through the links on our site. All of our content is based on objective analysis, and the opinions are our own.

This general fact should be kept in mind while assigning tasks to available work force. If the tasks that are not so complicated are assigned to very experienced workers, an unfavorable labor rate variance may be the result. The reason is that the highly experienced workers can generally be hired only at expensive wage rates.

Do you already work with a financial advisor?

labor rate variance

Direct labor rate variance is equal to the difference between actual hourly rate and standard hourly rate multiplied by the actual hours worked during the period. The variance would be favorable if the actual direct labor cost is less than the standard direct labor cost allowed for actual hours worked by direct labor workers during the period concerned. Conversely, it would be unfavorable if the actual direct labor cost is more than the standard direct labor cost allowed for actual hours worked. Hitech manufacturing company is highly labor intensive and uses standard costing system. The standard time to manufacture a product at Hitech is 2.5 direct labor hours. All tasks do not require equally skilled workers; some tasks are more complicated and require more experienced workers than others.

How much will you need each month during retirement?

This could occur if a higher-quality material was purchased or the suppliers raised their prices. If the cost of labor includes benefits, and the cost of benefits has changed, then this impacts the variance. If a company brings in outside labor, such as temporary workers, this can create a favorable labor rate variance because the company is presumably not paying their benefits. Requiring managers to determine what caused unfavorable variances forces them to identify potential problem areas or consider if the variance was a one-time occurrence. Requiring managers to explain favorable variances allows them to assess whether the favorable variance is sustainable. Knowing what caused the favorable variance allows management to plan for it in the future, depending on whether it was a one-time variance or it will be ongoing.

Standard Costing Outline

A common reason of unfavorable labor rate variance is an inappropriate/inefficient use of direct labor workers by production supervisors. Figure 8.4 shows the connection between the direct labor rate variance and direct labor time variance to total direct labor variance. If the actual hours worked are less than the standard hours at the actual production output level, the variance will be a favorable variance.

A positive value of direct labor rate variance is achieved when standard direct labor rate exceeds actual direct labor rate. Thus positive values of direct labor rate variance as calculated above, are favorable and negative values are unfavorable. The labor rate variance measures the difference between the actual and expected cost of labor. An unfavorable variance means that the cost of labor was more expensive than anticipated, while a favorable variance indicates that the cost of labor was less expensive than planned.

In this case, the actual hours worked per box are 0.20, the standard hours per box are 0.10, and the standard rate per hour is $8.00. This is an unfavorable outcome because the actual hours worked were more than the standard hours expected per box. As a result of this unfavorable outcome information, the company may consider retraining its workers, changing the production process to be more efficient, or increasing prices to cover labor costs.

Why You Can Trust Finance Strategists

An overview of these two types of labor efficiency variance is given below. For the past 52 years, Harold Averkamp (CPA, MBA) hasworked as an accounting supervisor, manager, consultant, university instructor, and innovator in teaching accounting online. He is the sole author of raleigh bookkeeping all the materials on AccountingCoach.com.

This is a favorable outcome because the actual hours worked were less than the standard hours expected. Labor rate variance is the difference between actual cost of direct labor and its standard cost. The difference due to actual amount paid and the standard rate per hour while the time spends during production remains the same. However, a positive value of direct labor rate variance may not always be good. When low skilled workers are recruited at a lower wage rate, the direct labor rate variance will be favorable however, such workers will likely be inefficient and will generate a poor direct labor efficiency variance.

In this case, the actual rate per hour is $7.50, the standard rate per hour is $8.00, and the actual hour worked is 0.10 hours per box. This is a favorable outcome because the actual rate of pay was less than the standard rate of pay. As a result of this favorable outcome information, the company may consider continuing operations as they exist, or could change future budget projections to reflect higher profit margins, among other things. With either of these formulas, the actual rate per hour refers to the actual rate of pay for workers to create one unit of product. The standard rate per hour is the expected rate of pay for workers to create one unit of product. The actual hours worked are the actual number of hours worked to create one unit of product.

An unfavorable outcome means you paid workers more than anticipated. The direct labor variance measures how efficiently the company uses labor as well as how effective it is at pricing labor. There are two components to a labor variance, the direct labor rate variance and the direct labor time variance.

Insurance companies pay doctors according to a set schedule, so they set the labor standard. They pay a set rate for a physical exam, no matter how long it takes. If the exam takes best expense report templates mesh longer than expected, the doctor is not compensated for that extra time. Doctors know the standard and try to schedule accordingly so a variance does not exist. If anything, they try to produce a favorable variance by seeing more patients in a quicker time frame to maximize their compensation potential. The following is a summary of all direct materials variances (Figure 8.6), direct labor variances (Figure 8.7), and overhead variances (Figure 8.8) presented as both formulas and tree diagrams.

If, on the other hand, less experienced workers are assigned the complex tasks that require higher level of expertise, a favorable labor rate variance may occur. However, these workers may cause the quality issues due to lack of expertise and inflate the firm’s internal failure costs. In order to keep the overall direct labor cost inline with standards while maintaining the output quality, it is much important to assign right tasks to right workers. Direct labor rate variance (also called direct labor price or spending variance) is the difference between the total cost of direct labor at standard cost (i.e. direct labor hours at standard rate) and the actual direct labor cost. The total direct labor variance is also found by combining the direct labor rate variance and the direct labor time variance. By showing the total direct labor variance as the sum of the two components, management can better analyze the two variances and enhance decision-making.

Leave a Comment

Your email address will not be published. Required fields are marked *

Shopping Cart